Date: 07 April 2016 , 00:00
News ID: 272

10% increase in HDGL productivity thanks to the new X-JET air knives at MMK Metalurji, Turkey

Danieli received the Final Acceptance Certificate for the new air-knife system installed in the existing Hot Dip Galvanizing Line, in January 2016.
10% increase in HDGL productivity thanks to the new X-JET air knives at MMK Metalurji, Turkey

The MMK Metalurji Dortyol project in 2008 involved the supply of a complete Danieli hot and cold mill complex.

The first X-Jet installation in 2009, Italy


At that time the X-Jet technology was not yet available for industrial production (the first X-Jet installation occurred in mid-2009, in Italy), and so the MMK hot-dip galvanizing line was equipped with the Danieli Kohler S-Jet air knives.
Since 2008 the HDGL production mix has progressively moved to include a higher percentage of thin strips with very thin coatings (including Z70), and so the initial air knives had become a limit to higher processing speed, in effect a bottleneck to higher throughput.
The decision to install X-Jets followed technical discussions and a thorough analysis of the expected production benefits. Thanks to the modular design of Danieli Kohler’s air knives, the revamping included the re-use of many parts of the existing equipment, minimizing the capital investment. Danieli supplied new X-Jet air knives with lip cleaners, new blowers with special piping, modifications to the existing roll rigs and to the associated maintenance, and electrical and automation equipment.


The new X-Jets were installed during a scheduled, one-week maintenance shutdown.
The performance of the X-Jets in terms of coating weight versus line speed was immediately seen as a step change compared to the previous production parameters.
After the revamping the HDGL is able to daily produce Z100 at 180 meters per minute, and tests have shown the X-Jets to be capable of running Z80 with 40 g/m2/side at 180 mpm.
As a result of the X-Jet’s performance, HDGL productivity has increased by approximately 10%, with a payback time of less than six months for MMK.

source: Danieli