Nan Ya shuts down No.1 MEG unit

Taiwan's Nan Ya Plastics is shutting down its No.1 MEG unit at Mailiao today for scheduled maintenance.
Nan Ya shuts down No.1 MEG unit

This 360,000 t/yr MEG production line will have a four-week-long overhaul and resume production in mid-September. Nan Ya subsequently then plans another four-week turnaround at its 360,000 t/yr No.3 MEG unit in line with its upstream cracker's maintenance.

Nan Ya's largest MEG production line, the 720,000 t/yr No.4 MEG unit, will have a month-long overhaul in November for a catalyst change.

Nan Ya has already had maintenance at its No.3 and No.4 lines in February and July respectively. It has four MEG production lines at Mailiao totalling 1.8mn t/yr.

Negative production margins are the reason for Nay Ya deciding to have two turnarounds at its MEG production lines this year. Naphtha-based MEG production margins were around $20/t lower than breakeven in first-half August, according to Argus data.

source: Argus Media